Working Party 01/12/2018

Working Party 01/12/2018

Here is the working party report from 01/12/2018

Attendees: 7
Team Leader: John Attridge

  1. Most of the effort was focussed on cleaning underneath the tender.
  2. The outside of the tender frame was undercoated where the last working party had got to.
  3. The grate shaker mechanism was cleaned and painted.
  4. Jim did some electrical work in the cab.

Picture attached.
Next working day: 15th December, team leader Dave Oliver.